You have two main paths. A like-for-like rebuild under the Mayor's Emergency Executive Order No. 1 can go up to 110% of the old home's footprint and height, in substantially the same location, and skips discretionary planning, Coastal and environmental review. A larger home has to meet current zoning, and in the Coastal Zone it can use Executive Order No. 8 to avoid a Coastal permit if it meets that order's criteria. Either way the house must meet today's building code. Going larger adds construction cost at roughly the same rate per square foot (our planning range is $400 to $700 per square foot for a rebuild with mid-to-upper finishes), plus City fees on area above 110% and possible property-tax reassessment.
Most Palisades owners we talk to start with the same question: should we rebuild what we had, or take the chance to build something bigger? The answer changes the permit path, the review time, the City fees, the property tax, and of course the construction budget. The rules behind each of those use a "110%" threshold, but not the same 110%, which is where a lot of confusion starts.
We're a design-build general contractor based in Studio City, currently building a single-story rebuild on a cleared Palisades lot. This guide explains each path in plain English and links every regulatory statement to its official source. It is general information, not legal or tax advice; the City's One-Stop Rebuilding Center and your own advisors can confirm how the rules apply to your address.
What are the two permit paths?
| Like-for-like (EO 1) | Larger, zoning-compliant | |
|---|---|---|
| Size limit | Up to 110% of the old footprint and height | Whatever current zoning allows |
| Location on the lot | Substantially the same location | Anywhere zoning allows |
| Old non-conforming setbacks, height, floor area | Can generally be kept | Must meet today's zoning |
| Planning and Coastal review | None (no discretionary, Coastal, environmental or Mello Act review) | Coastal Zone: none if EO 8 criteria are met, otherwise full Coastal review. Outside the Coastal Zone: generally none if zoning-compliant |
| Building code | Current code (or a 2019-code house rebuilt to its original approved design) | Current code |
| City fee waiver | Covers up to 110% of the original area | Covers up to 110%; fees on area above it |
| Property tax | 110% of square footage treated as substantially equivalent | Added area beyond that can be assessed |
Table: The like-for-like path compared with a larger rebuild
The first path comes from the Mayor's Emergency Executive Order No. 1 (EO 1). The larger path in the Coastal Zone comes from Emergency Executive Order No. 8 (EO 8). City Planning's rebuild FAQ, dated January 30, 2026, is the clearest official summary of both.
What does a like-for-like rebuild under EO 1 allow?
EO 1 defines an eligible project as one that replaces a structure damaged or destroyed by the January 2025 fires, for the same use, in substantially the same location, at no more than 110% of the footprint and height of what stood before. Within that envelope, the City Planning FAQ says the house can keep the old home's non-conforming yards, height, number of stories, floor area and parking, even where those no longer meet today's zoning.
It is more flexible than the name suggests. According to the FAQ, a like-for-like rebuild can:
- Shift the house on the lot, as long as it stays in substantially the same location.
- Add a basement, even if the old house didn't have one.
- Add an ADU, attached or detached, with a 10-foot setback from a canyon bluff or 25 feet from a coastal bluff.
- Rebuild supporting work such as retaining walls, foundations, utilities and driveways.
- Become fully two-story, if the second floor fits inside the massing allowed at 110% of the old home's tallest height. The FAQ gives the example of a house that was one story in front and two in back.
To document the old footprint and height, the City accepts prior permits, certificates of occupancy, County Assessor data, aerial and LiDAR imagery and similar records. LADBS keeps plans for many homes built after 1978, which you can request with an affidavit.
What doesn't EO 1 waive?
Three things catch people out.
- The building code still applies. EO 1 requires the current City building codes, with one narrow exception: a house originally designed and built to the 2019 California code can be rebuilt to that same approved design. For most Palisades homes, which are far older, the new house is built to today's structural, energy, accessibility and wildfire standards. Our rebuild cost guide covers the wildfire construction rules, fire sprinklers and the energy-code options in the Governor's orders.
- Anything outside the old footprint meets today's zoning. The FAQ is explicit: construction outside the previously existing footprint is subject to current zoning requirements.
- Private rules still apply. The City doesn't enforce CC&Rs or homeowners association rules, and a permit doesn't mean you comply with them. If your street has an HOA, its review can come before the City's.
Can I rebuild bigger, and how does the Coastal Zone change things?
Yes. A house larger than 110%, or one that moves or reshapes significantly, simply has to meet current zoning: setbacks, height and residential floor-area limits for your lot. You can check your parcel's zoning, hillside status and Coastal Zone status on ZIMAS.
Where the lot sits decides how much review that brings:
- Outside the Coastal Zone. The City Planning FAQ says a zoning-compliant single-family rebuild there generally needs no Planning review at all. The project goes through LADBS plan check like any new house.
- Inside the Coastal Zone, using EO 8. EO 8 exempts zoning-compliant single-family rebuilds from Coastal review when they meet its criteria. Those include the same number of units (plus an ADU), no lot splits or mergers, setbacks of 10 feet from a canyon bluff or 25 feet from a coastal bluff, and no significant impact on biological resources. A bluff analysis or a biologist's statement may be needed; ZIMAS shows whether your lot is flagged. The FAQ notes this replaces what would typically be an 18 to 24 month Coastal review with a process that may take days or a couple of months.
- Inside the Coastal Zone, not eligible for EO 8. The normal Coastal and Planning review applies, which is the slowest path.
EO 8 also gave every zoning-compliant single-family rebuild a few practical benefits: ministerial haul-route approval, use of a prevailing front-yard setback where one existed, and suspension of Low Impact Development stormwater rules for homes replacing a house built before September 2002.
How do the fee waiver and property tax change when I go larger?
City fees. A City ordinance that took effect on July 16, 2026 waives LADBS permit and clearance fees for rebuilds of up to 110% of the area of the damaged or destroyed structure, for owners who held the property on January 7, 2025. The City Attorney's report on the ordinance describes the 110% limit, an aggregate cap on total waivers, and a payback rule if the property is sold before a certificate of occupancy is issued. Local reporting confirms that fees for area above 110% are charged. A larger house keeps the waiver on its first 110%; it pays fees on the rest.
Property tax. Under California law, a rebuilt home that is "substantially equivalent" to the one lost keeps its prior base-year value. In December 2025 the LA County Assessor adopted a standard treating a rebuild of up to 110% of the original square footage, with comparable size, utility and function, as substantially equivalent. The Assessor's letter also warns that the emergency building orders and property-tax rules operate independently. A home that is larger than that can have the added value assessed. Ask the Assessor how it applies before you finalize the size.
Construction. More area costs more, at roughly the same rate per square foot. For a new home or rebuild with mid-to-upper finishes, our planning range is $400 to $700 per square foot of living space, including finishes and design and permit work, before government fees and site work.
An illustration, not a quote
Adding 800 square feet beyond a like-for-like rebuild, at $400 to $700 a foot, adds roughly $320,000 to $560,000 in construction alone. Then add City fees on the area above 110%, any engineering for a new structure or larger foundation, and possible reassessment of the added area.
What are the time and design trade-offs?
The like-for-like path is usually the quickest and the most predictable. There is no discretionary review, the old envelope is already established, and the design work is mostly about improving the plan inside it. EO 1 also directed City departments to complete initial permit reviews for all rebuild projects within 30 days of a complete application, and LADBS offers standard pre-approved plans for some rebuilds (see its wildfire information page).
A larger home buys design freedom: a better layout, a second story where there wasn't one, a different relationship to the garden or view. The costs are a longer design phase, more engineering, possibly a bluff or biological review in the Coastal Zone, and the fee and tax effects above. On a hillside lot, current floor-area limits may also be tighter than people expect, so check them before you design around a size.
Some owners split the difference: a like-for-like house with a basement or a new ADU, both of which EO 1 allows and neither of which counts against the main house's footprint.
How does the contract work on either path?
The contract rules are the same whichever path you choose. The Contractors State License Board states that rebuilding after a declared disaster is treated as a home improvement project, so the contract must be fixed-price, the down payment can't exceed $1,000 or 10% of the contract price (whichever is less), and later payments can't run ahead of the work completed.
That matches how we already work. Our construction contracts are fixed-price with payments tied to milestones such as foundation, framing, rough systems, drywall and finishes. The deposit is $1,000 or less, we provide unconditional lien releases with each payment, and any change is priced and approved in writing before the work starts. Many of our clients choose and buy their own finishes, such as tile, plumbing fixtures, lighting and appliances, with our help sourcing them, so the contract price covers the build and the installation. Each proposal also lists its exclusions, such as solar, low-voltage wiring, landscaping and hardscape, so you can see what still needs a budget.
A decision checklist
- Pull the records. Prior permits, plans from LADBS if they exist, and Assessor data, to establish the old footprint, height and square footage.
- Check the lot on ZIMAS. Coastal Zone, hillside, and coastal or canyon bluff flags each change the path.
- Test your wish list against all three 110% rules. Footprint and height (EO 1), area (fee waiver) and square footage (property tax).
- Price both versions. We can price a like-for-like scheme and a larger one side by side, so the decision rests on real numbers rather than a guess.
- Check private rules. CC&Rs and HOA approvals can constrain either path.
- Ask the City. The One-Stop Rebuilding Center can confirm eligibility for your address before you commit to a design.
If you're weighing the two options now, we're glad to walk through your lot and the numbers with you. You can also follow the rebuild we're building on our Pacific Palisades project page, compare delivery methods on our comparisons page, or try the ranges yourself in our pricing guide.
Sources
Rules and programs change. We link to the official source for every regulatory statement in this article; check it for the current version before you rely on it.
- Los Angeles City Planning: Frequently Asked Questions Related to Palisades Fire Rebuilds (January 30, 2026)
- Office of Mayor Karen Bass: Emergency Executive Order No. 1, revised March 18, 2025 (Expedited Community Rebuilding and Recovery)
- Office of Mayor Karen Bass: Emergency Executive Order No. 8 and Partially Revised No. 1 (July 23, 2025)
- Los Angeles City Attorney: report on the fee-waiver ordinance, LAMC 98.0419.1 (Council File 25-0006-S57, April 23, 2026)
- Palisades News: permit fees waived for Palisades rebuilds (ordinance effective July 16, 2026)
- LA County Assessor via Board of Supervisors: post-disaster property assessment standards (110% substantially-equivalent standard, December 2025)
- LADBS: 2025 Los Angeles Wildfires information (plan submittal, standard plans, soils and geology reports)
- Contractors State License Board: Rebuilding after the 2025 LA wildfires, contract and payment rules
- ZIMAS: City of Los Angeles zoning and parcel information